   नेपाल पूर्वाधार विकास कम्पनी लिमिटेडकाे निर्वाचन अधिकृतकाे कार्यलय उमेद्वारहरुकाे नाम फिर्ता लिने समय थप गरीएकाे सूचना              नेपाल पूर्वाधार विकास कम्पनी लिमिटेडकाे निर्वाचन कार्यक्रमकाे सूचना           नेपाल पूर्वाधार विकास कम्पनी लिमिटेडको तेस्रो चौथो, पाँचौ र छैटौ वार्षिक साधारण सभा सम्बन्धि सार्वजनिक सूचना         नेपाल पूर्वाधार विकास कम्पनी लिमिटेडको विशेष साधारण सभा सम्बन्धि सार्वजनिक सूचना      सुरुङमार्ग बन्छ, बन्नैपर्छ, कुनै न कुनै विकल्पमा बनाउँछौं      ‘काठमाडौं–हेटौंडा सुरुङमार्ग जसरी पनि बनाईन्छ, दायाँबायाँ हुँदैन’      सुरुङमार्ग बन्न नदिए हामी चुप लागेर बस्दैनौं        कार्यालय सरेको अत्यन्त जरुरी सूचना       हाम्रो मेगा प्रोजेक्टले नेपालको इतिहासमा ठूलो परिवर्तन ल्याउनेछ        NPBCL submits fresh financial closure report       सुरुङमार्गको पर्खाइमा राजधानी             

 

 

March 23, 2019
Special General Meeting
   
Aug 28, 2018 Submission of JDA with PowerChina to Provincial Government #3
   
Aug 23, 2018 Submission of JDA and Technical Proposal of PowerChina to MoPIT
   
July 25, 2018
Joint Development Agreement signing
   
June 06, 2018 Term Sheet Signing on Joint Development Agreement (JDA)
   
Feb 2018 Project Site Visit by PowerChina
   
Jan 13, 2018 Submission of Technical Proposal by PowerChina
   
Jan 11, 2018 Submission of Project Schedules by PowerChina
   
May 10, 2017
EPC Contract signing in China and Supplement Agreement on May 14, 2017
   
April 2, 2017 Additional MOU in-relation to Project Schematic Timeline
   
Sep 12, 2016 MOU for the Contract Model of KKHT Highway Project
   
March 11, 2016 Project Site Visits
   

March 2, 2016

Amendment and Validity Extension of MOU on Dec 18, 2015
   
Dec 18, 2015 MOU on allocation of Responsibility between NPBCL and PowerChina


Project Developments with PowerChina, China

April, 2018 Received letter from China Railway about their visit to Nepal for meeting with NPBCL and Government of Nepal for discussion regarding investment on the project. Meeting dates are being finalized by NPBCL.
   
2074 Chaitra Received letter from MOPIT for contract Agreement – extending the project by 3.5 years
   
2074 Poush Final Presentation on EIA done at MOPE. Comments received from Final updating of EIA ongoing as of Baisakh 2075 and will submitted soon for approval of Final EIA
   
November 2017 LOI received from China Railway to participate as equity partner at 80:20 ratio
   
September, 2017 Detailed Engineering Design/Detailed Feasibility Study Report review completion by China Railway
   
June, 2017 Cooperation Agreement signed with China Railway
   
May 2017 Power China/Sino Hydro Preliminary EPC signed.
   
2074 Kartik Scheduled Final Presentation on EIA at the Ministry of Population and Environment at end of Kartik, 2074, required for approval of Final EIA.
   
2074 Aswin Submission of Final Detailed Engineering Survey, Investigation and Detail Design Report to Ministry of Physical Infrastructure and Transport.
   
2074 Bhadra Published the Final Notice for EIA for public grievances if any in National Daily Newspaper
   
2073 Falgun Approval of Draft EIA report by Ministry of Population and Environment and request to publish the final notice for grievances
   
2073 Aswin Submission of draft EIA report and status report to Ministry of Physical Infrastructure and Transport
   
2072 Poush MoU with Sinohydro Corporation Ltd.
Completion of De
   
2072 Bhadra Status/Progress report to Ministry of Physical Infrastructure and Transport
   
2072 Jestha Status report to Ministry of Physical Infrastructure and Transport
   
2071 Chaitra Information on completion of financial closure to Ministry of Physical Infrastructure & Transport
   
2071 Mangsir Agreement with Exp Services Inc., Canada for Project Assessment Study
   
2071 Mangsir Submission of progress report to Ministry of Physical Infrastructure & Transport